The UPEIDA-funded 91.35 km Gorakhpur Link Expressway project is a four-lane, access-controlled expressway that connects Jaitpur in the Gorakhpur District with Salarpur on the Purvanchal Expressway in the Azamgarh District.
The land acquisition phase for this greenfield project began in February 2019 after it was initially announced in 2018. Apco Infratech and Dilip Buildcon began construction in February 2020 with a 36-month completion target. The project has a 110-meter right-of-way (ROW).
Estimated Cost of Gorakhpur Link Expressway Project | INR 5,877 Crores |
Total length of the project | 91.35 Kilometer |
Number of Lanes | 4 lanes and expandable up to 6 lanes |
Current Status of Gorakhpur Link Expressway | Under Construction (53% progress achieved) |
Expected Completion Deadline | March 2023 |
Owner of the project | Uttar Pradesh Expressways Industrial Development Authority (UPEIDA) |
Project Model | EPC (Engineering, Procurement and Construction) |
Route Map and Alignment of Gorakhpur Link Expressway
At Salarpur (District Azamgarh), on the Purvanchal Expressway, is where the expressway’s southern terminus is located. The districts of Azamgarh, Ambedkar Nagar, Sant Kabir Nagar, and Gorakhpur are all connected from there. The Ghaghara River is crossed along the journey.
The beginning and ending locations of the expressway are shown on the following unappealing map from UPEIDA’s website. The alignment of it on Google Maps can be followed here more effectively.
When it becomes available, a PDF route map for the Gorakhpur Link Road will be added here.
Latest Progress Update of Gorakhpur Link Expressway
Earthwork in Main Carriageway: | 76% |
C&G (Clearing & Grubbing) in Main Carriageway | 100% |
GSB (Granular Sub Base) in Main Carriageway | 53% |
WMM (Wet Mix Macadam) in Main Carriageway | 50% |
DBM (Dense Bituminous Macadam) in Main Carriageway | 46% |
Total Structures Completed | 295 completed out of 342 |
Overall Progress | 53% |
Also Read About – Ganga Expressway
Tenders and Contractor Details of Gorakhpur Link Expressway
Package details |
Working Contractor |
Pkg 1: Jaitpur (Dist. Gorakhpur) to Fulwariya (Dist. Ambedkar Nagar) [Km -0+817 to Km 47+500] | Apco Infratech |
Pkg 2: Fulwariya (Dist. Ambedkar Nagar) to Salarpur (Dist. Azamgarh) [Km 47+500 to Km 90.535] | Dilip Buildcon Ltd |
Also Read About – Ganga Expressway